Excel RFQs
Packages that left the register
Build from takeoff. Export CSV, paste into the Excel RFQ you already send. When the vendor files come back, drop them on Ingest — prices write onto the same lines.
10 packages · 12/15 vendor seats answered
| RFQ | Title | Commodity | Lines | Sent | Due | Vendors |
|---|---|---|---|---|---|---|
| RFQ-001 | Power transformer | Transformer | 1 | Aug 12 | Sep 4 | Hitachi EnergyReturnedGE VernovaReturned |
| RFQ-002 | 138 kV SF6 breakers | Breakers | 1 | Aug 18 | Sep 8 | Siemens EnergyReturnedMEPPISent |
| RFQ-003 | 138 kV disconnects Southern States BOM is 4 units. Takeoff is 6. | Disconnects | 1 | Aug 18 | Sep 8 | Southern StatesReturnedPascor AtlanticSent |
| RFQ-004 | CTs, CCVTs, arresters Issued before Addendum 3. CT qty on RFQ is still 7. | Instrument TXs | 3 | Aug 19 | Sep 8 | ABBReturnedTrench GroupSent |
| RFQ-005 | 34.5 kV metal-clad switchgear | Switchgear | 1 | Aug 14 | Sep 4 | Powell ElectricalReturnedEatonNo-bid |
| RFQ-006 | Substation steel | Steel | 3 | Aug 20 | Sep 9 | Valmont UtilityReturned |
| RFQ-007 | Foundations | Foundations | 2 | Aug 22 | Sep 8 | Capform ConcreteLate |
| RFQ-008 | Aluminum pipe bus and fittings | Bus & fittings | 2 | Aug 21 | Sep 9 | AFLReturned |
| RFQ-009 | MV power cable Control cable C-CAB-CTL was left off this package. | Cable | 1 | Aug 21 | Sep 9 | SouthwireReturned |
| RFQ-010 | Fence, rock, ground grid | Civil / yard | 3 | Aug 25 | Sep 9 | Border FenceReturned |